When more hours of labor time are necessary to complete a job than the standard allows, the labor efficiency variance is unfavorable.

Labor Efficiency Variance

The difference between the actual hours taken to complete a task and the standard hours allowed for the actual output, multiplied by the standard hourly labor rate.

Labor Time

The duration of time workers spend in the process of producing goods or providing services.

  • Determine the elements contributing to discrepancies in material and labor expenses in manufacturing processes.
  • Analyze the consequences of deviations on the cost and efficiency of materials.