The labor efficiency variance for the month is closest to:

A) $5,425 U
B) $5,425 F
C) $5,325 U
D) $5,325 F

Labor Efficiency Variance

The difference between the actual hours worked and the standard hours expected, multiplied by the standard hourly wage rate.

  • Comprehend the methodology for computing labor efficiency variance.
  • Determine the factors that distinguish a favorable (F) variance from an unfavorable (U) one.
verifed

Verified Answer

NS
Nitesh SinghOct 11, 2024
Final Answer: