Peterson Company estimates that overhead costs for the next year will be $6,520,000 for indirect labor and $550,000 for factory utilities.The company uses machine hours as its overhead allocation base.If 140,000 machine hours are planned for this next year,what is the company's plantwide overhead rate? (Round your answer to two decimal places.)

A) $0.02 per machine hour.
B) $50.50 per machine hour.
C) $45.75 per machine hour.
D) $3.93 per machine hour.
E) $0.25 per machine hour.

Plantwide Overhead Rate

An overhead allocation rate used throughout an entire plant or company to allocate indirect costs to products.

Overhead Allocation Base

A measure used to distribute overhead costs among various products or service units within a business.

Machine Hours

A measure of the amount of time machines are operated in the production process, commonly used as an allocation base for assigning overhead costs.

  • Calculate plantwide overhead rates.