Asked by

Marshaun Campbell
on Oct 19, 2024

verifed

Verified

Estimate to complete equals budget at completion minus schedule variance, i.e., ETC = BAC − SV.

Estimate to Complete

An updated projection of costs still required to complete all remaining project activities, considering current performance.

Budget at Completion

The total budget allocated for a project based on all estimated costs upon completion.

Schedule Variance

A project management metric indicating the difference between the planned and actual progress of a project.

  • Comprehend the methods for calculating and interpreting cost performance indices and variances.
verifed

Verified Answer

LN
Lucas NanceOct 22, 2024
Final Answer:
Get Full Answer